G R Infraprojects Transmission Project Boosts Madhya Pradesh Renewable Energy

G R Infraprojects Transmission
G R Infraprojects Transmission Project in MP (ARI)

G R Infraprojects Limited has recently been awarded a significant Letter of Intent (LOI) from REC Power Development and Consultancy Limited, a move that underscores its expanding role in India's critical infrastructure development. This substantial project focuses on establishing vital transmission systems to evacuate power generated from renewable energy (RE) zones located in Rajgarh and Neemuch in Madhya Pradesh. The LOI, dated August 27, 2025, signifies the company's commitment to building essential substations and transmission lines, thereby facilitating the smooth integration of clean energy into the national grid and bolstering the region's power infrastructure.

G R Infraprojects Secures Major Transmission Project in Madhya Pradesh

G R Infraprojects Limited has been awarded a significant Letter of Intent (LOI) from REC Power Development and Consultancy Limited, signaling a substantial expansion in its transmission infrastructure capabilities. This project, crucial for the state of Madhya Pradesh, involves establishing a robust transmission system to evacuate power from renewable energy (RE) zones in Rajgarh (1500 MW) and Neemuch (1000 MW). The LOI, received on August 27, 2025, marks a pivotal moment for the company as it undertakes the development of essential transmission infrastructure, including substations and transmission lines, aimed at efficiently channeling renewable energy into the grid.

Project Scope and Technical Specifications

The project's comprehensive scope encompasses the establishment of a 2x500 MVA, 400/220 kV Substation at Handia, coupled with the installation of 2x125 MVAr 420 kV Bus Reactors. Furthermore, it involves the construction of a new 220 kV Bus Section-II at the Neemuch Pooling Station (PS). To augment transformation capacity, three 500 MVA, 400/220 kV ICTs (3rd, 4th, and 5th) will be installed at the Neemuch Substation, along with associated bays. The project also details the construction of four 220 kV line bays at Neemuch PS for RE interconnection and a third 220 kV Bus Section at Neemuch PS, integrating a 220 kV Bus Sectionalizer and additional ICT augmentation.

Enhancing Grid Connectivity for Renewable Energy

A key objective of this initiative is to bolster the grid's ability to integrate large-scale renewable energy sources. The project includes the construction of three additional 220 kV line bays for RE interconnection and one 220 kV line bay specifically for Purvah Green Power Pvt. Ltd.'s RE interconnection. This strategic development ensures that the generated renewable power can be smoothly and efficiently transferred to the national grid, thereby supporting the country's clean energy targets. The focus on multiple interconnection points underscores the project's commitment to flexibility and scalability in handling diverse energy flows.

Substation Augmentation and Line Development

The project's technical blueprint also includes the installation of a 1x125 MVAR, 420 kV Bus Reactor at Pachora PS (400 kV Bus Section-II). It mandates the construction of four 400 kV line bays, with two each at Rajgarh (PG) and Pachora PS. Additionally, four 420 kV Switchable Line Reactors (Sw LRs) are to be installed, two at each of the specified locations. The project further specifies the installation of switching equipment for 400 kV line reactors, again with two units designated for Rajgarh (PG) and two for Pachora PS, ensuring comprehensive grid management capabilities.

Transmission Lines and Power Evacuation

The project involves the laying of extensive 400 kV Double Circuit (D/c) lines utilizing Quad ACSR/AAAC/AL59 Moose equivalent conductors. These lines will be equipped with associated line bays at both ends. Critically, each circuit will feature two 50 MVAr Switchable Line Reactors (Sw LRs) at both ends to manage power flow and voltage stability. The scope also includes similar 400 kV D/c lines connecting to the Pachora PS end, complete with corresponding bays and Sw LRs, ensuring efficient and stable power evacuation across the network.

Ensuring Power Stability with Reactors

The inclusion of Switchable Line Reactors (Sw LRs) is a critical engineering aspect of this project, designed to enhance the stability and reliability of the transmission network. These reactors are essential for controlling overvoltages, particularly during light load conditions, which are common in systems with high renewable energy penetration. By dynamically switching these reactors in or out of the circuit, operators can maintain optimal voltage levels, preventing equipment damage and ensuring uninterrupted power supply. This proactive approach to grid management is vital for integrating intermittent renewable sources.

Strategic Power Evacuation Routes

The project defines specific routes for power evacuation, including 400 kV D/c (Twin Moose) lines originating from the Handia Substation. These lines are crucial for connecting the RE projects to the main transmission grid. The detailed specifications for conductor types and the inclusion of line bays at both ends highlight the meticulous planning involved in ensuring seamless power transfer. The overall objective is to create a robust and efficient pathway for renewable energy generated in Madhya Pradesh to reach consumers, contributing to a greener energy mix.

Financial and Operational Framework

The annual transmission charges for this significant project are pegged at ₹367.07 crore, with an Operation and Maintenance (O&M) period extending over 35 years. The project is slated to be executed on a Build, Own, Operate, and Transfer (BOOT) basis. A key aspect of the project's timeline is its completion within 24 months from the acquisition of the Special Purpose Vehicle (SPV). This timeline underscores the urgency and strategic importance placed on bolstering the transmission infrastructure for renewable energy in the region.

Project Execution and Timeline

The execution of this project under the BOOT model signifies a long-term commitment from G R Infraprojects. The company will be responsible for the entire lifecycle of the transmission assets, from construction and commissioning to operation and eventual transfer. The stringent 24-month completion deadline from SPV acquisition emphasizes the project's critical nature and the need for efficient project management. This accelerated timeline reflects the government's push to expand renewable energy capacity and the associated transmission infrastructure.

Annual Revenue and Operational Period

With annual transmission charges set at approximately ₹367.07 crore, the project represents a substantial revenue stream for G R Infraprojects over its 35-year operational lifespan. This predictable revenue, tied to the crucial function of power transmission, offers a stable financial outlook for the company. The long-term nature of the contract also allows for amortizing the significant capital investment required for developing such large-scale transmission infrastructure, making it an attractive proposition for infrastructure developers.

Company's Confirmation and Contact Information

G R Infraprojects Limited has formally communicated the receipt of this LOI to the stock exchange, requesting that this information be noted for official records. The company has designated Company Secretary Sudhir Mutha as the primary point of contact for any further inquiries or additional details regarding this substantial transmission project. His role will be crucial in disseminating information and ensuring transparency throughout the project's development and execution phases.

Ensuring Stakeholder Communication

Maintaining open and clear communication with all stakeholders, including investors, regulatory bodies, and the public, is paramount. The designation of a specific contact person like Sudhir Mutha facilitates this process, ensuring that queries are addressed promptly and accurately. This proactive approach to information dissemination builds trust and confidence in the company's operations and its ability to manage complex infrastructure projects effectively, especially those vital for the nation's energy transition.

Future Outlook and Strategic Importance

This project is strategically vital for both G R Infraprojects and Madhya Pradesh's renewable energy goals. By securing this LOI, the company positions itself as a key player in the development of essential infrastructure required to harness the state's vast renewable energy potential. The successful execution of this project will not only contribute to the company's revenue growth but also play a significant role in strengthening the power transmission network, supporting the national agenda for sustainable energy development.

Key Takeaways for Investors and Stakeholders

The acquisition of this significant transmission project by G R Infraprojects presents a compelling opportunity for stakeholders. The project's substantial annual revenue of ₹367.07 crore, coupled with a 35-year operational period under a BOOT model, indicates strong long-term financial prospects. The project's critical role in evacuating renewable energy from major SEZs in Madhya Pradesh highlights its strategic importance in the nation's energy transition. Investors can anticipate a stable income stream and potential for growth as the company continues to expand its footprint in the vital power transmission sector.

Financial Implications and Revenue Streams

The financial implications of this project are considerable, with the annual transmission charges providing a predictable and robust revenue stream. This ₹367.07 crore per annum figure, guaranteed over 35 years, offers a solid foundation for the company's financial planning and future investments. The BOOT structure ensures that G R Infraprojects will benefit directly from the operational phase, maximizing returns on its investment in this critical infrastructure asset, which is essential for the reliable integration of renewable energy sources into the national grid.

Strategic Expansion in Renewable Infrastructure

Securing this transmission project marks a significant strategic advancement for G R Infraprojects in the renewable energy infrastructure domain. The project's focus on connecting large-scale RE projects underscores the company's commitment to supporting the country's transition towards cleaner energy sources. By developing and managing these vital transmission links, G R Infraprojects is not only enhancing its market position but also contributing tangibly to India's renewable energy targets, reinforcing its role as a key infrastructure developer in the green energy ecosystem.

Project Component

Key Specifications

Financials & Operational Details

Project Award

Letter of Intent (LOI) from REC Power Development and Consultancy Limited

Received on August 27, 2025

Location

Madhya Pradesh (Rajgarh & Neemuch RE Zones)

Evacuation of power from 1500 MW (Rajgarh) and 1000 MW (Neemuch) SEZs

Substation Development

Handia: 2x500 MVA, 400/220 kV S/s; Pachora PS: 400 kV Bus Section-II

Includes 2x125 MVAr 420 kV Bus Reactors at Handia; 1x125 MVAR, 420 kV Bus Reactor at Pachora

Neemuch Substation Augmentation

New 220 kV Bus Section-II; Augmentation of 400/220 kV ICTs (3rd, 4th, 5th)

Construction of 4 No. 220 kV line bays for RE interconnection; Additional 3 No. 220 kV line bays

Transmission Lines

400 kV D/c lines (Quad ACSR/AAAC/AL59 Moose equivalent)

Associated line bays at both ends; 50 MVAr Sw LRs per circuit at both ends

Grid Stability Measures

Switchable Line Reactors (Sw LRs)

Installation of 420 kV Sw LRs at Rajgarh and Pachora PS

Annual Transmission Charges

₹367.07 Crore

O&M Period: 35 years

Execution Model

Build, Own, Operate, and Transfer (BOOT)

Completion within 24 months of SPV acquisition

Company Contact

Sudhir Mutha (Company Secretary)

For additional project information

From our network :

Comments

Rated 0 out of 5 stars.
No ratings yet

Add a rating

Important Editorial Note

The views and insights shared in this article represent the author’s personal opinions and interpretations and are provided solely for informational purposes. This content does not constitute financial, legal, political, or professional advice. Readers are encouraged to seek independent professional guidance before making decisions based on this content. The Mag Post website and the author(s) of the content makes no guarantees regarding the accuracy or completeness of the information presented.

bottom of page